Turn the Hall You Already Have into a 140 kW-per-rack Liquid-Cooled AI Floor.

Direct-to-chip and rear-door heat-exchange deployments engineered into facilities you already control — slab, electrical and thermal assessment, CDU and manifold design, installation and commissioning, without a greenfield build.

RETROFIT · AIR TO DIRECT-TO-CHIPAir · 15 kWDLC · 132 kWSame cage · 6–10 week cutover
140 kW
per rack after retrofit
W32–W45
warm-water loops, free cooling most of the year
8–10 wks
typical row retrofit, assessment to live

Who This Is For

  • Enterprises with an air-cooled hall at 8–15 kW per rack that now needs GPU rows
  • Colocation tenants who want NVL72-class racks in their existing cage
  • Operators of older facilities who need to extend asset life into the liquid-cooled era
  • Teams that have been told their building cannot host GPUs and want a second opinion

What's Included

Retrofit Assessment

Structural review of slab and raised floor for 1,600 kg racks, electrical capacity to the row, chilled-water or condenser-water availability, pathway and containment.

Cooling Architecture

Direct-to-chip with row or in-rack CDUs where density demands it; rear-door heat exchangers where 40–60 kW per rack is the target; hybrid designs for mixed rows.

Hydraulic Design

Secondary loop sizing, manifold and quick-disconnect layout, coolant chemistry, filtration, leak detection and isolation strategy.

Electrical Upgrade

New or upgraded busway and PDUs to 415 V, breaker coordination, UPS review and generator load check.

Installation

Pipework, CDU placement, manifolds, rack integration, pressure and leak testing, flushing and fill.

Commissioning

Thermal mapping under load, flow balancing, alarm integration into BMS/DCIM, and operator training on loop maintenance.

Reference Specifications

Starting points. Every engagement is engineered to the workload, site and budget in front of us.

Density range40–60 kW per rack with rear-door HX; 100–140 kW per rack with direct-to-chip liquid
CDU optionsIn-rack (to ~100 kW), row-level (to ~1.5 MW), facility-level skids; CoolIT, Motivair, Vertiv, Boyd
Loop temperaturesFacility water W32 or W45 supply; secondary loop 25 °C supply / 45 °C return typical
Heat rejectionExisting chillers, dry coolers for free cooling, or heat reuse to building hot-water systems
StructuralPoint-load and distributed-load checks for 1,600 kg loaded racks on slab or raised floor
MonitoringFlow, pressure, temperature and leak sensing integrated to BMS, DCIM and the cluster's observability stack

How We Deliver

  1. 1

    Assessment

    Weeks 1–2

    Site survey, drawings review, structural and electrical capacity confirmation. Output: feasibility report with options and budget.

  2. 2

    Design

    Weeks 2–4

    Hydraulic, electrical and mechanical packages, landlord or AHJ submissions, equipment selection and ordering.

  3. 3

    Install

    Weeks 4–8

    Pipework, CDUs, manifolds, busway and PDUs installed with the hall live where required.

  4. 4

    Commission

    Weeks 8–10

    Pressure test, flush and fill, thermal mapping under synthetic load, alarm and runbook handover.

Questions We Get Asked

Can the retrofit happen while the hall stays in production?

Usually yes. We phase work by row, isolate new pipework from live equipment, and schedule tie-ins to existing plant during agreed maintenance windows.

Our facility has no chilled water. Can we still go liquid?

Yes. Dry coolers or packaged chillers on the roof or pad feed a facility loop; with warm-water design temperatures most Texas sites free-cool for the majority of the year.

What about leaks?

Modern cold-plate systems run at low pressure with dripless quick-disconnects, and we install leak detection at every manifold and CDU with automatic isolation. The loop is pressure-tested before any rack is energised.

Request a Quotation

Pre-tagged as Liquid-cooling retrofit. A solutions engineer responds the same business day.

Next: Power & Cooling Infrastructure

Creates a lead in our CRM and routes to a solutions engineer.